Wet weather sets back reopening of Lancaster's Greyhound Bridge

Wet weather sets back reopening of Lancaster's Greyhound Bridge
Greyhound Bridge under construction. Photo taken in April 2018 by Chris Coleman/AE Yates LtdGreyhound Bridge under construction. Photo taken in April 2018 by Chris Coleman/AE Yates Ltd
Greyhound Bridge under construction. Photo taken in April 2018 by Chris Coleman/AE Yates Ltd

The bridge had been due to reopen on Sunday September 23, but constant rain showers over recent weeks have prevented good progress with work to waterproof the deck.

County Coun Keith Iddon, cabinet member for highways and transport, said: “The waterproofing process is crucial to protect the repairs to the concrete and metalwork which have been the core part of this major scheme to refurbish the Greyhound Bridge.

Hide Ad
Hide Ad

“Waterproofing requires the section of the bridge deck being treated to be completely clean and free of all water. Unfortunately, the constant showery weather over the last few weeks means that we have not been able to get this work done.

“Our bridges team built four weeks into the programme to carry out the waterproofing. Under dry conditions this is enough time to waterproof the deck four times over, but the changeable weather means we’ve only been able to complete a third of it.

“We’re really looking forward to reopening the bridge, and this situation is very frustrating for everyone, not least those who have been trying to carry out the work and keep to schedule.

“Having reviewed the weather forecast for the coming weeks we have decided to defer the opening of the bridge for two weeks. We’re hoping for better luck, and will take every opportunity we get to make progress.”

Hide Ad
Hide Ad

After the deck has been waterproofed, it will be resurfaced, a process which is much less weather dependent.

Resurfacing of Cable Street from Water Street and Greyhound Bridge Road is taking place this week, as scheduled, between 7pm and 11pm from Monday September 17 to Sunday September 23.

The advertised changes to all Stagecoach bus services will now begin from Monday October 8 rather than Monday September 24.

The £4m refurbishment project to the Greyhound Bridge began in January to make sure the bridge retains the strength to carry big HGVs.

You can find out more by searching ‘Greyhound Bridge’ at www.lancashire.gov.uk.