Road works: 22/11/13

Latest news.

Latest news.

0
Have your say

The following summary of planned new and ongoing road improvements over the coming week is correct as of Friday 22 November but could be subject to change due to weather conditions or unforeseen circumstances. All our improvement work is carried out with the aim of causing as little disruption as possible.

M6 Junction 33 Lancaster

A project is taking place to repair bridges carrying the M6 over local roads. The work involves routine concrete repairs and installing new safety barriers along the southbound carriageway just north of Junction 33. The work is due to be completed by Friday 20 December. Some lane closures and a 50mph speed limit will be in place.

M6 Junction 38 Tebay

A contraflow system is in place on the M6 near Junction 38 at Tebay as part of a major refurbishment of a motorway bridge which carries the M6 over the River Lune. Southbound traffic will be directed into lanes on the northbound carriageway while the bridge is closed for the repairs. Two lanes will run in each direction and a 40mph speed limit will be in place. The project is due to be completed by March 2014

M55 Junction 1 Broughton

Resurfacing work, drainage repairs and lighting installation is being carried out around Broughton Interchange, north of Preston, affecting both the eastbound and westbound M55 links to and from the southbound M6. All the work will be taking place between 8pm and 6am each night with lane closures in place. Some full closures of the motorway carriageways will also be necessary, which will be publicised on the motorway in advance. Diversions will be in place when the road is closed, and the project is due to be completed by Sunday 22 December.

Lancashire County Council is also carrying out improvement work at the roundabout linking Junction 1 of the M55 with the A6 at Broughton to reduce delays at one of Preston’s worst congestion hotspots. The scheme will widen the junctions with the A6, add traffic controls to all junctions, and make it safer to use for pedestrians and cyclists by installing new crossings while retaining the existing subways. The work is expected to be completed by December, and diversions will be in place when roads are closed.

M60 Junction 11 Irlam

Maintenance work is being carried out at Junction 11 of the M60 which will require some slip roads to be closed overnight, between 10pm and 5am. The project is due to be completed by Saturday 30 November. Diversions will be in place when slip roads are closed.

M60 Junction 24 Denton

A major project to boost safety and reduce congestion at Junction 24 of the M60 at the Denton Island roundabout where the motorway meets the M67 and the A57 get underway on Monday 11 November. The first phase of the project is due to be completed by February next year, with a second phase due to start in March. No work will take place over the Christmas and New Year holidays, and the whole project is due to be completed by June 2014. All of the work during the first phase will take place overnight, and involve lane closures and speed limit reductions on the slip roads and roundabout. At times, full slip road closures will be needed overnight with clearly-signed diversions in place.

M60 Junction 25 Bredbury to Junction 1 Stockport

Overnight maintenance work is being carried out on both sides of the M60 between Junctions 25 and 1, which includes drainage work, improvements to junction signs and resurfacing. The work will take place between 10pm and 5am during weekdays and between 10pm and 7am at weekends, and will require some lane and slip road closures. It is due to be completed by Monday 16 December, and diversions will be in place when slip roads are closed.

A590 Lindale

Work is underway to repair and improve drainage along the A590 around Lindale in Cumbria. The project will involve single lane closures of the dual carriageway for just over a mile, and is due to be completed by Friday 20 December. A 50mph speed limit will be in place when lanes are closed.

A590 / A5092 Greenodd

Work is taking place to build a new roundabout linking the A590 to the A5092 at Greenodd, with the aim of reducing congestion and improving safety. The A590 currently forms a T-junction with the A5092, with traffic having to pull into a gap in the central reservation to turn right towards Ulverston. The project is due to be completed by February 2014.

A short section of the A5092 will be closed from 6.00am Saturday 23 November until 6.00am Monday 25 November as part of the programme. A signed diversion route, suitable for all types of vehicles, will take drivers along the A590, A595 and then back onto the A5092.Traffic lights will also control vehicles along the A590 as there will only be a single lane for 300m through the roadworks during the closure.

A595 Parton

There will be daytime traffic signals with shuttle working for re-cabling and sign works from 9.30am until 3.30pm beginning on Monday 11 November and ending on Saturday 30 November.

A595 Inkerman Terrace

There will be daytime lane closures with switching in both directions for survey works from 9.30am until 3.30pm until Thursday 9 December.

A66 Beckces Junction to Highgate

There will be daytime traffic signals for surfacing works from 9.30am to 3.30pm. Work is due be completed by Friday 20 December.

A66 Lamplugh Roundabout Footway

There will be 24 hour convoy working in place for construction of footways to verges and crossing points. Work will be completed by Wednesday 11 December.